1. Turbine & Generator Protection Test

    1) Emergency Governor Test

    2) Governor 특성 Test

    3) Emergency Trip Test

 

2. 발전기 계통병입(Generator Initial Synchronization)

 

3. Generator Block Load(House Load) Test

 

4. Generator Load Test (1/4, 2/4, 3/4, 4/4 Load)

 

5. 4/4 Load Rejection(Dump) Test

 

6. Boiler 연소시험 (Combustion Test) 및 Tuning

 

7. Turbine Bearing Inspection

 

8. Boiler, Turbine 각 Master Tuning

 

9. 보일러 제어설비 동특성 시험 (ABC Load Swing Test)

 

10. Load Run Back Test

 

11. APS(Auto Plant Start&Stop) Test

 

12. AFC & AGC(Auto Frequency Control & Auto Governor Control) Test

 

13. Initial Load Test(24 Hour)

 

14. Plant 신뢰도 운전시험 (Reliability Test, 240 Hour)

 

15. 인수 성능시험 (Performance Test)

 

16. 인수 보증시험 (Guaranteed Test)

 

17. 상업운전 개시 및 준공(COD ; Commercial Operation Day)